Activity Projected Date Purpose
Field Work Ongoing Gather field data for use in design.
Preliminary Design Open House December 2006 Present and gain input on proposed design.
Right-of-way Discussions with Property Owners Ongoing. Anticipated conclusion 2010. Negotiate purchase of necessary right-of-way for construction of Sawmill Parkway Extension.
Begin Construction No sooner than Spring 2010. Initiate construction activities for Sawmill Parkway Extension.

 

Community Engagement Schedule

Meeting Projected Date Purpose
Open House #1 June 29, 2004 Gain input for preliminary corridor alternatives
Open House #2 September 29, 2004 Present study corridor alternatives
Open House #3 January 19, 2005 Preferred corridor, land use and traffic discussion
Open House #4 March 22, 2005 Present feasible alignments
Open House #5 June 28, 2005 Present preferred alignment
Open House #6 December 6, 2006 Discuss current state of plan development