Project Design
Schedule
| Activity |
Projected
Date |
Purpose |
| Field
Work |
Ongoing |
Gather
field data for use in design. |
| Preliminary
Design Open House |
December
2006 |
Present
and gain input on proposed design. |
| Right-of-way
Discussions with Property Owners |
Ongoing.
Anticipated conclusion 2010. |
Negotiate
purchase of necessary right-of-way for construction of Sawmill
Parkway Extension. |
| Begin
Construction |
No
sooner than Spring 2010. |
Initiate
construction activities for Sawmill Parkway Extension. |
Community Engagement
Schedule
| Meeting |
Projected
Date |
Purpose |
| Open
House #1 |
June
29, 2004 |
Gain
input for preliminary corridor alternatives |
| Open
House #2 |
September
29, 2004 |
Present
study corridor alternatives |
| Open
House #3 |
January
19, 2005 |
Preferred
corridor, land use and traffic discussion |
| Open
House #4 |
March
22, 2005 |
Present
feasible alignments |
| Open
House #5 |
June
28, 2005 |
Present
preferred alignment |
| Open
House #6 |
December
6, 2006 |
Discuss
current state of plan development |
|
|