March 22, 2005

There were a total of 68 responses received for this survey. 49 surveys were turned in at the Open House and 19 were received afterwards in the form of surveys or correspondence.

1. After reviewing the feasible alternatives for theSawmill Parkway Extension, which one do you prefer?

 
At Open House
After Open House
Total
Alternate 1
6
3
9
Alternate 2
2
6
8
Alternate 3
5
3
8
Alternate 4
14
6
20

2. Tonight we discussed some design parameters for the SPE. Please indicate your opinions regarding some of those design elements.

A. Should the entire length of the Parkway be lighted?

 
At Open House
After Open House
Total
Yes
5
2
7
No
35
10
45

B. Should there be lighting only at intersections?

 
At Open House
After Open House
Total
Yes
24
9
33
No
15
5
20

C. Should there be no lighting along the Parkway?

 
At Open House
After Open House
Total
Yes
14
5
19
No
19
3
22

D. Should the Parkway have a bike path?

 
At Open House
After Open House
Total
Yes
34
11
45
No
10
4
14

If yes, should the bike path be on one side of the Parkway or on both sides?

 
At Open House
After Open House
Total
One Side
13
2
15
Both Sides
19
8
27

E. Should the right-of-way for the Parkway be expanded to accommodate varying width of median?

 
At Open House
After Open House
Total
Yes
21
4
25
No
16
9
25

F. Please indicate your preferences regarding ways in which the Parkway can be screened for existing homes and structures (check all that apply).

 
At Open House
After Open House
Total
 Earth Mounds
31
11
42
 Trees
38
12
50
 Fencing
8
3
11
 None
1
0
1